May 25, 2001
revised Oct 28, 2003
Internal reviews of NuMI Technical Components
Installation Reviews of NuMI/MINOS Devices
---------------------------------------------
DESIGN REVIEWS:
We are in the process of closing out design reviews by responding to previous
review comments.
NuMI/MINOS REVIEWS:
A combined list of reviews needed and completed for NuMI and MINOS is posted at this link. It includes design reviews, installation reviews,
operation reviews
and ESH/QA reviews. Often parts of the reviews overlap.
(see this link
for a list of completed technical component design reviews.)
REVIEW PROCESS/SCHEDULE:
Below is a list of review dates and reviewers for various technical
reviews of NuMI Beam line technical components.
These reviews are coordinated by Bruce Baller, Nancy Grossman, Rich Andrews
and/or Gina Rameika.
Nominally, review of each topic will be proceeded as:
o Assessment review
o interim review
o final DESIGN review
o Installation/operation review as necessary (often for a system)
Review materials will be posted on the web, to the extent possible, and the web
address sent to the reviewers in advance. The reviewers will be requested to
send their comments within one week from the review day.
All reviews will be open to everyone in NuMI Project and MINOS
collaboration. Any interested individuals can and are welcome to attend
and send their comments.
Final reviews may consist of responding to comments from previous reviews and
informing the reviewers of the where they can view the responses.
Back to Top of Page
PROPOSED REVIEW DATES AND REVIEWERS FOR DESIGN REVIEWS
----------------------------------
Back to Top of Page
1.1.1 Primary Beamline
=====
Primary beamline Magnet System
Contents: System design & installation
Interim: Apr 2, 23-24, 2002 Director's Reviews **DONE**
Final: Nov 1, 2002 (Beam Optics & magnet power supply) **DONE**
Final response to comments: **DONE**
Mar/Apr, 2003 (Beam Optics & magnet power supply)
Reviewers:
Dave Capista, Bob Ducar, Tom Kobilarcik, Jerry Leibfritz,
Dave McGinnis, Joel Misek, Shekhar Mishra, Dave Pushka, Wes Smart
Primary beamline instrumentation & Beam Permit System (see below)
Assessment: July 26, Aug 14 2001 **DONE**
Interim: Oct 14 2002 **DONE**
Interim: Mar 4, 2003 (Main Injector/NuMI BPM Review) **DONE**
Final: Oct 24, 2003 **DONE**
Reviewers:
Jim Crisp, Paul Czarapata, Rick Ford, Mike Gerardi, Greg Vogel,
Wally Kissel, Phil Martin, Gina Rameika, Nancy Grossman, Rich Neswold,
Craig Moore, Ralph Pasquinelli, Stan Pruss, Bob Webber, Kamran Vaziri,
Jim Zagel
Reviewers Oct 2002 (multiwire design focus)
Terry Anderson, James Crisp, Rick Ford, Dave Johnson, Karen Kephart,
Walter Kissel, John Krider, Eric Prebys, Rob Reilly, Vic Scarpine,
Dan Schoo, Gianni Tassotto
Reviewers for Oct 24, 2003 review, see review web page
(http://www-numi.fnal.gov/numwork/reviews/oct_2403.html).
Beam Optics & magnet power supply specification
Contents: Calculation with magnet + power supply, beam stability,
regulation
Assessment: Jun 28 2001 2:00-4:00 **DONE**
Interim: Dec 11 2001 **DONE**
Interim 2: Sep 2002 (MI/NuMI interfacing focus) **DONE**
Final: Nov 1 2002 (beamline sensitivities) **DONE**
Reviewers:
Phil Martin, Craig Moore, Shekhar Mishra, Don Edwards, Mike Syphers
Elvin Harms, George Krafczyk, Alexandr Drozhdin, John Johnstone
Mike Gerardi, Mike Andrews
Reviewers (Sep 2002):
Craig Moore, Shekhar Mishra, David Johnson, Alberto Marchionni,
Alexandr Drozhdin, John Johnstone, Terry Anderson, Bruce Baller
Reviewers (Nov 2002):
George Krafczyk, David Johnson, Paul Czarapata, John Johnstone,
Jim Hylen, Wes Smart, Ming-jen Yang
Beam Extraction Permit System (also see Primary beam instrumentation review)
Assessment: Aug 17, 2001 **DONE**
Final: Dec 2003 NEED
Reviewers:
Phil Martin, Shekhar Mishra, Ralph Pasquinelli, Stan Pruss,
Dave Capista, Gerry Jackson, Greg Vogel, Charles Briegel,
Paul Czarapata, Wally Kissel, Bob Mau, Dave Johnson,
Mike Andrews, Doug Michael, Rob Plunkett, Nancy Grossman,
Gina Rameika, Adam Para, Craig Moore
Kicker Fluorinert Cooling System Design
The purpose of this review is to collectively and constructively evaluate
the final design plans and details for this very critical cooling system.
Interim/Final June 14, 2002 **DONE**
Reviewers:
Sam Childress, Bob Ducar, Ray Lewis, Dave Pushka, Rob Reilly,
John Riordan, Karl Williams
BPM - use of digital down conversion electronics
Review requirements for NuMI BPMs and hear presentations from RF&I on
the use of digital down conversion (DDS) BPM's in order to try to
determine what is appropriate for NuMI.
June 25, 2002 **DONE**
Reviewers:
Sam Childress, Craig Moore, Valeri Makeev, Gianni Tassotto, James Crisp,
Jim Zagel, Mike Church, Bob Webber, Peter Prieto, Brian Chase,
Ralph Pasquinelli
Back to Top of Page
1.1.2 Neutrino Beam Devices
=====
Target and Target baffle
Assessment: Dec 18 2001 (final for target) **DONE**
Final: Aug 1 2002 (Baffle, baffle & target carrier) **DONE**
Reviewers (Assessment): BSpAG, Bob Bernstein, Dave Pushka,
Sam Childress, Peter Lucas, Bruce Baller
Reviewers (Design & engineering):
Mark Messier, Kris Anderson, Andy Stefanik, Vladimir Sidorov,
Sam Childress, Jim Kilmer, Pat Hurh, Dave Ayres, Victor Zarucheyskiy
Horn design, prototype & production program
Asessment: April 18 1998 **DONE**
Interim: April 16 1999 **DONE**
Final: Aug 10 2001 9:00-12:00 **DONE**
Reviewers:
Andy Stefanik, Dave Pushka, Bob Wands, Mark Reichanadter,
Ioanis Kourbanis, Larry Bartoszek, Danny Snee, Fritz Lange
Shielding of neutrino beam device area
Assessment: Jul 27 2001 9:00-12:00 **DONE**
Final: covered in Radiation Safety Review
Reviewers:
John Anderson, Mike Gerardi, Dave Pushka, Nancy Grossman,
Lee Hammond, Harry Ferguson, Russ Rucinski, Tony Leveling,
Gina Rameika, Cat James, TJ Sarlina, Mike Andrews,
Bob Bernstein
Instrumentation & monitoring in target hall (includes BDOT & cross hairs)
Assessment: Oct 18 2001 **DONE**
Final: Nov 18 2002 **DONE**
Reviewers:
Craig Moore, Phil Martin, Rick Ford, Gina Rameika, Adam Para,
Gary Feldman, Sam Childress, Sacha Kopp, Bob Bernstein,
Alberto Marchionni
Reviewers (Nov 2002):
Rick Ford, Adam Para, Frank Nezrick, Bob Ducar, Al Legan,
Lee Hammond, Brain Kramper
Target Hall Air System
Final: Aug 2003 **DONE**
Reviewers:
Dave Pushka, Kris Anderson, Rick Ford, Peter Kasper, Gary
Lautenschlager, Alexander Martinez, Rich Stanek, Del Allspach,
Lee Hammond & Bob Ducar
Hot Horn Handling Review
Interim: Aug 2001 **DONE**
Final: Feb 2002 **DONE**
Reviewers:
Dave Boehnlein, Don Cossairt, Mike Gerardi, Fritz Lange, Phil
Martin, Mike May, Rob Reilly
Final Reviewers (2002):
Dave Ayres, Dave Boehnlein, Don Cossairt, Rob Reilly
Back to Top of Page
1.1.3 Power Supplies
=====
Horn Transmission Line
Assessment: Jul 10 2001 9:00-12:00 **DONE**
Interim: Feb 26 2002 **DONE**
Final: Apr 23 2003 1:00-3:00 2NE **DONE**
Reviewers:
Mike May, Kris Anderson, Howie Pfeffer, Steve Hays,
Chris Jensen, Bill Markel, Dave Pushka, Phil Martin,
Jim Kilmer, Jim Hylen, Frank Nezrick
Final Reviewers (2003):
Kris Anderson, Bill Markel, Dave Pushka, Jim Hylen, Frank Nezrick,
Dave Tinsley, Ken Bourkland
Horn Power Supply (as part of horn system review initially)
Assessment: Apr 18 1998 **DONE**
Interim: Apr 16 1999 **DONE**
Final: Aug 13 2001 **DONE**
Magnet Power Supply
Assessment: Jul 11 2001 **DONE**
Final: Nov 1, 2002 (Beam Optics & magnet power supply) **DONE**
Final response to comments:
Mar/Apr, 2003 (Beam Optics & magnet power supply) **DONE**
Back to Top of Page
1.1.4 Absorber
=====
Decay pipe & Windows
Contents: cooling, radiation level, vacuum, ES&H review readiness
Assessment: Jul 9 2001 2:00- 5:00 12NW **DONE**
Final: Final reviews follow FESHM, Decay Pipe completed in May 2002
Reviewers:
Jim Klen, Mike Gerardi, John Anderson, Tony Leveling,
Nancy Grossman, Doug Jensen, Rich Stanek, Bob Sanders,
Sam Childress, Gina Rameika, Mike Andrews
Hadron Absorber
Contents: design, cooling, monitoring, installation
Assessment: Jun 12 2001 **DONE**
Final: Nov 20 2001 **DONE**
Reviewers:
Dave Eartly, Mike Gerardi, Tony Leveling, Jim Kilmer, Mike Andrews,
Mark Reichanadter, TJ Sarlina, Sacha Kopp, Dan Johnson, Kris Anderson
Back to Top of Page
1.1.5 Beam Monitoring
=====
Beam Monitoring System
Assessment: Dec 10 2001 **DONE**
Interim: Jul 24, 2002 9-12 1 North **DONE**
Final: Mar 2003 **DONE**
Reviewers:
Gary Feldman, Alberto Marchionni, Jim Hylen, Vittorio Paolone,
Doug Michael, Stan Wojcicki, Bob Bernstein, Adam Para
Reviewers (July 2002):
Mike Gerardi, Kamran Vaziri, Jim Hylen, Pat Hurh, Alberto Marchionni,
Stephen Pordes, Wes Smart, Mike Andrews, Dave Pushka
Back to Top of Page
1.1.7 Infrastructure
=====
Integrated picture
Contents: Cooling, HVAC, fire protection, FIRUS, ICATV, access
requirements, personnel limits including their controls and
monitoring
Assessment: Jul 12 2001 (part I) 9:00-12:00 12NW **DONE**
Jul 20 2001 (partII) 9:00-12:00 12NW **DONE**
Final: Mar 6 2002 **DONE**
Reviewers:
Dave Capista, Duane Plant, Dan Johnson, Steve Hays,
Russ Rucinski, Rob Plunkett, TJ Sarlina, Cat James,
Sam Childress, Jim Hylen, Nancy Grossman, Mike Andrews
RAW systems
Assessment: Oct 24 2001 **DONE**
For remainder of RAW reviews, see below.
Reviewers:
Duane Plant, Dan Johnson, Steve Hays, Russ Rucinski, John Peoples,
Mike Gerardi, Nancy Grossman, Tony Leveling, Gina Rameika,
TJ Sarlina, Mike Andrews
Water Systems Validation Review (LCW, RAW)
US LCW Final Sep/Oct 2002 (US LCW) **DONE**
RAW Systems Nov 2002 (Horns) **DONE**
RAW Systems Oct/Nov 2003 (Target) in progress
RAW Systems Oct/Nov 2003 (Hadron Absorber) in progress
RAW Systems Oct/Nov 2003 (Decay) in progress
Reviewers US LCW:
Maurice Ball, Richard Schmitt
Reviewers Horn RAW:
Maurice Ball, Richard Schmitt, Jim Hylen, Mike Gerardi
Reviewers Hadron Absorber RAW:
Maurice Ball, Richard Schmitt, Cat James, Mike Gerardi
Reviewers Decay Pipe RAW:
Maurice Ball, Richard Schmitt, Cat James, Mike Gerardi
Reviewers Target RAW:
Maurice Ball, Richard Schmitt, Jim Hylen, Mike Gerardi
Decay Vacuum System Validation Review
Final: May 2003 **DONE**
Reviewers:
Jim Klen, Bill Soyars
Back to Top of Page
1.1.1 & 1.1.3 Kicker
=============
Kicker magnets and Kicker power supply
Interim: Feb 1 2002 **DONE**
Final: Jul 1, 2002 1-3pm 1N **DONE**
Final (BD/EE support): Mar/Apr 2003 (ongoing series of meetings) **DONE**
Reviewers:
Dave Capista, Elvin Harms, George Krafczyk, Fritz Lange,
Terry Anderson, Bruce Hanna, Dave Pushka, Bob Ducar
Reviewers (July 2002):
George Krafczyk, Paul Czarapata, Greg Vogel, Bruce Hanna, Bob Ducar,
Dave Pushka, Dave Johnson, Dave Tinsley, Bill Boettinger
Reviewers Final (BD/EE support):
George Krafczyk, Dan Wolff (more?)
Back to Top of Page
System integration
==================
Workshop on Integrated Installation schedule
Part 1 upstream Sep 5 2001 **DONE**
Part 2 upstream Sep 27 2001 **DONE**
Part 3 downstream Oct 25 2001 **DONE**
Integrated Installation Schedule Review
Part 4 Review Mar 20-21 2002 **DONE**
Director's Review, Dec 4 2002 **DONE**
Reviewers:
Dave Ayres, Bob Brooker, Delmar Miller, Pat Hurh, Joel Misek,
John Voirin
Workshop on Risk Assessment
Part 1 Apr 2002 **DONE**
Part 2 Oct 8 2002 **DONE**
Commissioning plan of primary beam and neutrino devices
Assessment: Oct 19 2001 **DONE**
Interim: Nov 5 2002 (workshop) **DONE**
Final: Sent out for comments in Nov 2002, received March **DONE**
Reviewers 2001:
Shekhar Mishra, Dave Johnson, Dave Capista, Phil Martin,
Stan Pruss, Herman White, Rick Ford, Wally Kissel, Bob Mau,
Gerry Jackson
Sent for comments 2002:
Shekhar Mishra, Dan Johnson, Bob Mau, Gina Rameika,
Stan Wojcicki
Review of Accident Conditions
Assessment Nov 28 2001 **DONE**
Interim/Final Mar 2003 **DONE**
Back to Top of Page
Radiation safety reviews
Contents: Shielding, including BLBM, environment monitoring system,
air activation, ground water protection, RSS
Assessment: Jul 17, 2002 1-3pm **DONE**
Final: Jul 2003 **DONE**
Reviewers:
John Anderson, Mike Gerardi, Sam Childress, Alan Wehmann,
Wayne Schmitt, Gina Rameika, Mike Andrews, Craig Moore, Kamran Vaziri,
Byron Lundberg, Don Cossairt
Integrated Look at Controls
Assessment: Part of Infrastructure Reviews
Interim: Mar 2003 (Level 3 manager review) **DONE**
Final: Apr 2003 **DONE**
Reviewers:
Dave Capista, Geoff Pearce, Alec Habig, Pete Borders,
Ralph Pasquinelli, Paul Czarapata, Craig Moore, John Elias,
Marvin Johnson, Wally Kissel, Bob Mau
Reviewers Final:
Greg Vogel, Casey Seino, Al Franck, Dan Stenman, Al Legan, Paul Allcorn,
Brian Kramper
Back to Top of Page
Installation Reviews
====================
US Installation (See link to review web site) **DONE**
DS Installation (See link to review web site) **DONE**
*****************************************************************************
Follow this link to get to completed reviews.
Back to Top of Page
|