Summer'04_Shutdown





Project Start:
Project Finish:
8/23/04
12/7/04


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
Kicker Installation
16 days9/8/049/29/04 94%
2
Re-locate MI Instrumentation from NuMI Kicker Region (MI602)
3 days9/8/049/10/04Vacuum tech[300%]100%
3
Install Kicker Magnet Stands
1 day9/13/049/13/04Ironworker[200%]100%
4
Polarity check of Kicker Magnet
1 day9/14/049/14/04Engineer/Physicst0%
5
Install Kicker Magnets
1 day9/15/049/15/04Ironworker[300%]100%
6
Connect Kicker vacuum
1 day9/16/049/16/04Vacuum tech[200%]100%
7
Pump down and leak check
1 day9/17/049/17/04Vacuum tech[200%]100%
8
Rough Align Kicker Magnets
1 day9/20/049/20/04Surveyor[300%]100%
9
Connect fluorinert cooling system
2 days9/21/049/22/04Welder,LCW Tech100%
10
Terminate and connect Kicker Cables
5 days9/23/049/29/04EE Tech[200%]100%
11
Complete HV101 Recycler Shielding Installation
31 days8/23/0410/4/04 100%
12
Rotate recycler IP609
1 day8/23/048/23/04Mech. Tech[400%]100%
13
Isolate and disconnect waterlines
1 day8/23/048/23/04LCW Tech[200%]100%
14
HV101-2 main shielding
3 days8/24/048/26/04Mech. Tech[300%]100%
15
HV101-3 main shields
3 days8/27/048/31/04Mech. Tech[300%]100%
16
HV101-4 main shields
3 days9/1/049/3/04Mech. Tech[300%]100%
17
HV101-5 main shields
3 days9/4/049/8/04Mech. Tech[300%]100%
18
Reconnect jumpers and cables
3 days9/9/049/13/04 100%
19
HV101-1,2 gap shields
2 days9/14/049/15/04Mech. Tech[300%]100%
20
HV101-1 endshields
2 days9/16/049/17/04Mech. Tech[300%]100%
21
HV101-2 endshields
2 days9/20/049/21/04Mech. Tech[300%]100%
22
HV101-3 endshields
2 days9/22/049/23/04Mech. Tech[300%]100%
23
HV101-3,4 gap shields
2 days9/24/049/27/04Mech. Tech[300%]100%
24
HV101-4,5 gap shields
2 days9/28/049/29/04Mech. Tech[300%]100%
25
HV101-5 endshields
2 days9/30/0410/1/04Mech. Tech[300%]100%
26
Reconnect and test LCW
1 day10/4/0410/4/04LCW Tech[200%]100%
27
Trim Magnet Installation
37 days8/23/0410/12/04 100%
28
Install Trim Magnets & Stands in Extraction Area & xover
15.5 days8/23/049/13/04Ironworker[200%]100%
29
HT102 support
1 day8/23/048/23/04Ironworker[300%],Mech. Tech[200%]100%
30
Vt103 support
1 day8/24/048/24/04Ironworker[300%],Mech. Tech[200%]100%
31
HT105 support
1 day8/26/048/26/04Ironworker[300%],Mech. Tech[200%]100%
32
VT106 support
1 day8/27/048/27/04Ironworker[400%],Mech. Tech[200%]100%
33
HT107 support
1 day8/30/048/30/04Ironworker[300%],Mech. Tech[200%]100%
34
Transport and mount HT102
0.5 days9/9/049/9/04Ironworker[300%],Mech. Tech[200%]100%
35
Transport and mount VT103
0.5 days9/9/049/9/04Ironworker[300%],Mech. Tech[200%]100%
36
Transport and mount HT105
0.5 days9/10/049/10/04Ironworker[300%],Mech. Tech[200%]100%
37
Transport and mount VT106
0.5 days9/10/049/10/04Ironworker[300%],Mech. Tech[200%]100%
38
Transport and mount HT107
0.5 days9/13/049/13/04Ironworker[300%],Mech. Tech[200%]100%
39
Install Stub Trim Magnets & Stands in Stub
7.5 days9/13/049/22/04Ironworker[300%]100%
40
VT108 support
1 day9/13/049/14/04Ironworker[300%],Mech. Tech[200%]100%
41
HT109 support
1 day9/14/049/15/04Ironworker[300%],Mech. Tech[200%]100%
42
VT110 support
1 day9/15/049/16/04Ironworker[300%],Mech. Tech[200%]100%
43
VT111 support
1 day9/16/049/17/04Ironworker[300%],Mech. Tech[200%]100%
44
HT112 support
1 day9/17/049/20/04Ironworker[300%],Mech. Tech[200%]100%
45
Transport and mount VT108
0.5 days9/20/049/20/04Ironworker[300%],Mech. Tech[200%]100%
46
Transport and mount HT109
0.5 days9/21/049/21/04Ironworker[300%],Mech. Tech[200%]100%
47
Transport and mount VT110
0.5 days9/21/049/21/04Ironworker[300%],Mech. Tech[200%]100%
48
Transport and mount VT111
0.5 days9/22/049/22/04Ironworker[300%],Mech. Tech[200%]100%
49
Transport and mount HT112
0.5 days9/22/049/22/04Ironworker[300%],Mech. Tech[200%]100%
50
Insall SY 200 turn bump magnet stand
2 days9/23/049/24/04Ironworker[300%],Mech. Tech[200%]100%
51
Transport & moiunt SY 200 turn bump magnet
1 day9/27/049/27/04Ironworker[300%],Mech. Tech[200%]100%
52
Rough Align Trim Magnets
3 days10/6/0410/8/04Surveyor[300%]100%
53
Electrical connections to trim magnets & 200 turn bump
2 days10/11/0410/12/04EE Tech[200%]100%
54
LCW connections
2 days10/11/0410/12/04LCW Tech[300%]100%
55
Instrumentation Installation
49 days8/23/0410/28/04 98%
56
Install carrier pipe pumps
5 days8/23/048/27/04Vacuum tech,Welder100%
57
Install instrumentation supports
10.5 days8/30/049/13/04Ironworker[400%]99%
58
VP101support
0.5 days8/30/048/30/04Ironworker[300%],Mech. Tech[200%]100%
59
HP101 support
0.5 days8/30/048/30/04Ironworker[300%],Mech. Tech[200%]100%
60
PM101 support
0.5 days8/31/048/31/04Ironworker[300%],Mech. Tech[200%]100%
61
RWM support
0.5 days9/1/049/1/04Ironworker[300%],Mech. Tech[200%]100%
62
Toroid support
0.5 days9/1/049/1/04Ironworker[300%],Mech. Tech[200%]100%
63
HP102 support
0.5 days9/2/049/2/04Ironworker[300%],Mech. Tech[200%]100%
64
VP103 support
0.5 days9/2/049/2/04Ironworker[300%],Mech. Tech[200%]100%
65
HP104 support
0.5 days9/3/049/3/04Ironworker[300%],Mech. Tech[200%]100%
66
VP105 support
0.5 days9/3/049/3/04Ironworker[300%],Mech. Tech[200%]100%
67
PM105 support
0.5 days9/6/049/6/04Ironworker[300%],Mech. Tech[200%]100%
68
VP106 support
0.5 days9/6/049/6/04Ironworker[300%],Mech. Tech[200%]100%
69
HP107 support
0.5 days9/7/049/7/04Ironworker[300%],Mech. Tech[200%]100%
70
PM107 support
0.5 days9/7/049/7/04Ironworker[300%],Mech. Tech[200%]100%
71
VP108 support
0.5 days9/8/049/8/04Ironworker[300%],Mech. Tech[200%]100%
72
PM108 support
0.5 days9/8/049/8/04Ironworker[300%],Mech. Tech[200%]100%
73
HP109 suupport
0.5 days9/9/049/9/04Ironworker[300%],Mech. Tech[200%]100%
74
VP110 support
0.5 days9/9/049/9/04Ironworker[300%],Mech. Tech[200%]100%
75
VP111 support
0.5 days9/10/049/10/04Ironworker[300%],Mech. Tech[200%]100%
76
HP112 support
0.5 days9/10/049/10/04Ironworker[300%],Mech. Tech[200%]100%
77
PM112 support
0.5 days9/13/049/13/04Ironworker[300%],Mech. Tech[200%]100%
78
Swab out magnets
2 days8/30/048/31/04Vacuum tech[200%]100%
79
Check magnets for obstructions
2 days9/1/049/2/04Engineer/Physicst[200%]70%
80
Install Instrumentation & vacuum pipe (BPM's, PMs, toroid, RWM)
20 days9/3/049/30/04Vacuum tech[300%]100%
81
Install VP101
1 day9/3/049/3/04Vacuum tech[300%]100%
82
Install HP101
1 day9/6/049/6/04Vacuum tech[300%]100%
83
Install PM101
1 day9/7/049/7/04Vacuum tech[300%]100%
84
Install RWM
1 day9/8/049/8/04Vacuum tech[300%]100%
85
Install Toroid
1 day9/9/049/9/04Vacuum tech[300%]100%
86
Install HP102
1 day9/10/049/10/04Vacuum tech[300%]100%
87
Install VP103
1 day9/13/049/13/04Vacuum tech[300%]100%
88
Install HP104
1 day9/14/049/14/04Vacuum tech[300%]100%
89
Install VP105
1 day9/15/049/15/04Vacuum tech[300%]100%
90
Install PM105
1 day9/16/049/16/04Vacuum tech[300%]100%
91
Install VP106
1 day9/17/049/17/04Vacuum tech[300%]100%
92
Install HP107
1 day9/20/049/20/04Vacuum tech[300%]100%
93
Install PM107
1 day9/21/049/21/04Vacuum tech[300%]100%
94
Install VP108
1 day9/22/049/22/04Vacuum tech[300%]100%
95
Install PM108
1 day9/23/049/23/04Vacuum tech[300%]100%
96
Install HP109
1 day9/24/049/24/04Vacuum tech[300%]100%
97
Install VP110
1 day9/27/049/27/04Vacuum tech[300%]100%
98
Install VP111
1 day9/28/049/28/04Vacuum tech[300%]100%
99
Install HP112
1 day9/29/049/29/04Vacuum tech[300%]100%
100
Install PM112
1 day9/30/049/30/04Vacuum tech[300%]100%
101
Install loss monitors
10 days10/1/0410/14/04Inst. Tech[200%]100%
102
Rough align Instrumentation & vacuum pipe
7 days9/27/0410/5/04Surveyor[300%]100%
103
Install vacuum pumps and stands
10 days10/6/0410/19/04Vacuum tech[200%]100%
104
Terminate and connect Cables (Instrumentation, vacuum, etc.)
17 days10/6/0410/28/04Inst. Tech[300%]100%
105
Pump down and Commission Vacuum System
5 days10/20/0410/26/04Vacuum tech[300%]75%
106
Electrical Work
22 days8/23/049/21/04 100%
107
Pull Remaining Cables (Instr.,TLM, vacuum, etc.)
22 days8/23/049/21/04Electrician[500%]100%
108
Alignment Work
77 days8/23/0412/7/04 62%
109
Install control in carrier tunnel (upper hobbit)
1 day8/23/048/23/04Surveyor[300%]100%
110
Rough align stub magnets (6)
3 days8/24/048/26/04Surveyor[300%],Mech. Tech100%
111
Re-reference HV101-1 and HV101-6
2 days8/27/048/30/04Surveyor[300%]100%
112
Remove 2 sight riser plugs at MI-60
1 day8/26/048/26/04Ironworker[300%]100%
113
Vertical drops @ 4 SR (2 @MI-60 + SR1+SR2)
4 days8/31/049/3/04Surveyor[300%]100%
114
Level run between MI-60 to SR2 (Pre-Tgt) aprox 1500 ft
5 days9/6/049/10/04Surveyor[300%]100%
115
Tie Stub to Pre-Tgt network (through Carrier Tunnel) area
5 days9/13/049/17/04Surveyor[300%]100%
116
Tie Stub network to MI-60 (ties to SRs)
3 days9/20/049/22/04Surveyor[300%]100%
117
Final alignment of magnets MI thru Q104
9 days10/11/0410/21/04Surveyor[300%]100%
118
Final alignment of magnets and inst. Q104 thru NuMI stub
21 days10/22/0411/19/04Surveyor[300%]40%
119
Final alignment of magnets and inst. ds of hobbit door thru Horn2
12 days11/22/0412/7/04Surveyor[300%]0%
120
Re-align D614 at Mi-60
0.5 days11/22/0411/22/04Surveyor[300%]0%
121
Miscellaneous Jobs
65.5 days8/23/0411/22/04 46%
122
Remove 614-1 MI dipole and store in alcove
0.5 days8/23/048/23/04Mech. Tech[300%]100%
123
Install drip tray over LCW pipe
1 day8/23/048/23/04Mech. Tech[200%]100%
124
Remove hoses on Q111,Q112
0.25 days8/24/048/24/04LCW Tech100%
125
Install cooling plates on Q111,Q112
2 days8/24/048/26/04Mech. Tech[200%]100%
126
Connect LCW to Q111,Q112 and cooling plates
1 day8/26/048/27/04LCW Tech100%
127
Install additional fans
2 days8/27/048/31/04Mech. Tech[200%]0%
128
Recycler Dept specify final locations of temp probes
1 day8/31/049/1/04Engineer/Physicst0%
129
Move temp probes to new locations if necessary
1 day9/1/049/2/04Mech. Tech[200%]0%
130
Re-insert MI-60 sight riser plugs
1 day9/23/049/23/04Ironworker[300%]0%
131
Reinstall 614-1 at Mi-60
0.5 days11/22/0411/22/04Mech. Tech[300%]0%
132
Final Preparations for Beam
16 days10/29/0411/19/04 1%
133
Power supply tests (evenings)
15 days11/1/0411/19/04EE Tech[200%]0%
134
Subsystem checkout
9 days10/29/0411/10/04All support groups1%
135
BPMs
8 days10/29/0411/9/04 0%
136
Verify channels
2 days10/29/0411/1/04 0%
137
Verify readback/polarity
2 days11/2/0411/3/04 0%
138
Verify timing
2 days11/4/0411/5/04 0%
139
BPM plot working?
2 days11/8/0411/9/04 0%
140
Profile monitors
9 days10/29/0411/10/04 0%
141
Verify motor control
1 day10/29/0410/29/04 0%
142
Clearing foil voltage?
1 day11/1/0411/1/04 0%
143
SWIC plot working?
2 days11/2/0411/3/04 0%
144
Verify channels
1 day11/4/0411/4/04 0%
145
Verify readback/polarity
2 days11/5/0411/8/04 0%
146
Verify timing
2 days11/9/0411/10/04 0%
147
BLMs
8 days10/29/0411/9/04 13%
148
Verify channels
1 day10/29/0410/29/04 100%
149
High voltage?
1 day11/1/0411/1/04 0%
150
Verify readback/polarity
2 days11/2/0411/3/04 0%
151
Verify timing
2 days11/4/0411/5/04 0%
152
BLM plot working?
2 days11/8/0411/9/04 0%
153
TLMs
8 days10/29/0411/9/04 0%
154
Verify channels
1 day10/29/0410/29/04 0%
155
High voltage?
1 day11/1/0411/1/04 0%
156
Verify gas flow
1 day11/2/0411/2/04 0%
157
Verify readback/polarity
1 day11/3/0411/3/04 0%
158
Verify timing
2 days11/4/0411/5/04 0%
159
loss tracking
2 days11/8/0411/9/04 0%
160
Toroids
6 days10/29/0411/5/04 0%
161
Verify channels
1 day10/29/0410/29/04 0%
162
Verify readback/polarity
1 day11/1/0411/1/04 0%
163
Verify timing
2 days11/2/0411/3/04 0%
164
Beam budget Monitor
2 days11/4/0411/5/04 0%
165
Resistive Wall Monitor
6 days10/29/0411/5/04 0%
166
Readout in place, working?
1 day10/29/0410/29/04 0%
167
Verify channels
2 days10/29/0411/1/04 0%
168
Verify readback/polarity
2 days11/2/0411/3/04 0%
169
Verify timing
2 days11/4/0411/5/04 0%
170
Vacuum
8 days10/29/0411/9/04 0%
171
Verify channels
2 days10/29/0411/1/04 0%
172
Verify readback/polarity
2 days11/2/0411/3/04 0%
173
High voltage?
1 day11/4/0411/4/04 0%
174
Vacuum plot working?
2 days11/5/0411/8/04 0%
175
Alarms and limits?
1 day11/9/0411/9/04 0%
176
LCW/RAW
7 days10/29/0411/8/04 0%
177
Verify channels
2 days10/29/0411/1/04 0%
178
Verify readback/polarity
2 days11/2/0411/3/04 0%
179
LCW plot working?
2 days11/4/0411/5/04 0%
180
Alarms and limits?
1 day11/8/0411/8/04 0%
181
Beam Permit System
8 days10/29/0411/9/04 0%
182
200 Modules
4 days10/29/0411/3/04 0%
183
Verify channels
1 day10/29/0410/29/04 0%
184
Does permit make-up?
1 day11/1/0411/1/04 0%
185
Does disconnecting cable pull permit?
2 days11/2/0411/3/04 0%
186
204 Modules
8 days10/29/0411/9/04 0%
187
Verify channels
2 days10/29/0411/1/04 0%
188
Verify timing
2 days11/2/0411/3/04 0%
189
Analog readback working/polarity?
2 days11/4/0411/5/04 0%
190
Trip points correct?
1 day11/8/0411/8/04 0%
191
Does violating trip point pull permit?
1 day11/9/0411/9/04 0%
192
Alignment
8 days10/29/0411/9/04 0%
193
Network residuals look reasonable?
3 days10/29/0411/2/04 0%
194
Do location of devices match current beamsheet?
5 days11/3/0411/9/04 0%
195
Final alignment within specified tolerances?
5 days11/3/0411/9/04 0%
196
Field direction checks (all magnets) (end of shutdown)
1 day11/9/0411/9/04Interlock tech,Engineer/Physicst0%
197
Beamline Testing (exercise components)
7 days11/11/0411/19/04Engineer/Physicst[500%]0%
198
Ready for commissioning with beam
1 day11/22/0411/23/04 0%
199
Scheduled End of Shutdown (13 Weeks)
1 day11/22/0411/22/04 0%

Resources


IDNameGroupMax UnitsPeak Units
1Ironworker 600%1,400%
2Pipefitter 400%0%
3Electrician 500%0%
4Surveyor 300%600%
5Inst. Tech 400%0%
6Vacuum tech 300%300%
7EE Tech 300%200%
8Engineer/Physicst 200%500%
9LCW Tech 400%0%
10Interlock tech 100%100%
11All support groups 100%100%
12Welder 100%0%
13Mech. Tech 400%900%

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete
2Re-locate MI Instrumentation from NuMI Kicker Region (MI602)Vacuum tech72 hrs9/8/049/10/04100%
3Install Kicker Magnet StandsIronworker16 hrs9/13/049/13/04100%
4Polarity check of Kicker MagnetEngineer/Physicst8 hrs9/14/049/14/040%
5Install Kicker MagnetsIronworker24 hrs9/15/049/15/04100%
6Connect Kicker vacuumVacuum tech16 hrs9/16/049/16/04100%
7Pump down and leak checkVacuum tech16 hrs9/17/049/17/04100%
8Rough Align Kicker MagnetsSurveyor24 hrs9/20/049/20/04100%
9Connect fluorinert cooling systemWelder16 hrs9/21/049/22/04100%
9Connect fluorinert cooling systemLCW Tech8 hrs9/21/049/21/04100%
10Terminate and connect Kicker CablesEE Tech80 hrs9/23/049/29/04100%
12Rotate recycler IP609Mech. Tech32 hrs8/23/048/23/04100%
13Isolate and disconnect waterlinesLCW Tech16 hrs8/23/048/23/04100%
14HV101-2 main shieldingMech. Tech72 hrs8/24/048/26/04100%
15HV101-3 main shieldsMech. Tech72 hrs8/27/048/31/04100%
16HV101-4 main shieldsMech. Tech72 hrs9/1/049/3/04100%
17HV101-5 main shieldsMech. Tech72 hrs9/4/049/8/04100%
19HV101-1,2 gap shieldsMech. Tech48 hrs9/14/049/15/04100%
20HV101-1 endshieldsMech. Tech48 hrs9/16/049/17/04100%
21HV101-2 endshieldsMech. Tech48 hrs9/20/049/21/04100%
22HV101-3 endshieldsMech. Tech48 hrs9/22/049/23/04100%
23HV101-3,4 gap shieldsMech. Tech48 hrs9/24/049/27/04100%
24HV101-4,5 gap shieldsMech. Tech48 hrs9/28/049/29/04100%
25HV101-5 endshieldsMech. Tech48 hrs9/30/0410/1/04100%
26Reconnect and test LCWLCW Tech16 hrs10/4/0410/4/04100%
28Install Trim Magnets & Stands in Extraction Area & xoverIronworker248 hrs8/23/049/13/04100%
29HT102 supportIronworker24 hrs8/23/048/23/04100%
29HT102 supportMech. Tech16 hrs8/23/048/23/04100%
30Vt103 supportIronworker24 hrs8/24/048/24/04100%
30Vt103 supportMech. Tech16 hrs8/24/048/24/04100%
31HT105 supportIronworker24 hrs8/26/048/26/04100%
31HT105 supportMech. Tech16 hrs8/26/048/26/04100%
32VT106 supportIronworker28 hrs8/27/048/27/04100%
32VT106 supportMech. Tech16 hrs8/27/048/27/04100%
33HT107 supportIronworker24 hrs8/30/048/30/04100%
33HT107 supportMech. Tech16 hrs8/30/048/30/04100%
34Transport and mount HT102Ironworker12 hrs9/9/049/9/04100%
34Transport and mount HT102Mech. Tech8 hrs9/9/049/9/04100%
35Transport and mount VT103Ironworker12 hrs9/9/049/9/04100%
35Transport and mount VT103Mech. Tech8 hrs9/9/049/9/04100%
36Transport and mount HT105Ironworker12 hrs9/10/049/10/04100%
36Transport and mount HT105Mech. Tech8 hrs9/10/049/10/04100%
37Transport and mount VT106Ironworker12 hrs9/10/049/10/04100%
37Transport and mount VT106Mech. Tech8 hrs9/10/049/10/04100%
38Transport and mount HT107Ironworker12 hrs9/13/049/13/04100%
38Transport and mount HT107Mech. Tech8 hrs9/13/049/13/04100%
39Install Stub Trim Magnets & Stands in StubIronworker180 hrs9/13/049/22/04100%
40VT108 supportIronworker24 hrs9/13/049/14/04100%
40VT108 supportMech. Tech16 hrs9/13/049/14/04100%
41HT109 supportIronworker24 hrs9/14/049/15/04100%
41HT109 supportMech. Tech16 hrs9/14/049/15/04100%
42VT110 supportIronworker24 hrs9/15/049/16/04100%
42VT110 supportMech. Tech16 hrs9/15/049/16/04100%
43VT111 supportIronworker24 hrs9/16/049/17/04100%
43VT111 supportMech. Tech16 hrs9/16/049/17/04100%
44HT112 supportIronworker24 hrs9/17/049/20/04100%
44HT112 supportMech. Tech16 hrs9/17/049/20/04100%
45Transport and mount VT108Ironworker12 hrs9/20/049/20/04100%
45Transport and mount VT108Mech. Tech8 hrs9/20/049/20/04100%
46Transport and mount HT109Ironworker12 hrs9/21/049/21/04100%
46Transport and mount HT109Mech. Tech8 hrs9/21/049/21/04100%
47Transport and mount VT110Ironworker12 hrs9/21/049/21/04100%
47Transport and mount VT110Mech. Tech8 hrs9/21/049/21/04100%
48Transport and mount VT111Ironworker12 hrs9/22/049/22/04100%
48Transport and mount VT111Mech. Tech8 hrs9/22/049/22/04100%
49Transport and mount HT112Ironworker12 hrs9/22/049/22/04100%
49Transport and mount HT112Mech. Tech8 hrs9/22/049/22/04100%
50Insall SY 200 turn bump magnet standIronworker48 hrs9/23/049/24/04100%
50Insall SY 200 turn bump magnet standMech. Tech32 hrs9/23/049/24/04100%
51Transport & moiunt SY 200 turn bump magnetIronworker24 hrs9/27/049/27/04100%
51Transport & moiunt SY 200 turn bump magnetMech. Tech16 hrs9/27/049/27/04100%
52Rough Align Trim MagnetsSurveyor72 hrs10/6/0410/8/04100%
53Electrical connections to trim magnets & 200 turn bumpEE Tech32 hrs10/11/0410/12/04100%
54LCW connectionsLCW Tech48 hrs10/11/0410/12/04100%
56Install carrier pipe pumpsVacuum tech40 hrs8/23/048/27/04100%
56Install carrier pipe pumpsWelder40 hrs8/23/048/27/04100%
57Install instrumentation supportsIronworker272 hrs9/1/049/13/0416%
58VP101supportIronworker12 hrs8/30/048/30/04100%
58VP101supportMech. Tech8 hrs8/30/048/30/04100%
59HP101 supportIronworker12 hrs8/30/048/30/04100%
59HP101 supportMech. Tech8 hrs8/30/048/30/04100%
60PM101 supportIronworker12 hrs8/31/048/31/04100%
60PM101 supportMech. Tech8 hrs8/31/048/31/04100%
61RWM supportIronworker12 hrs9/1/049/1/04100%
61RWM supportMech. Tech8 hrs9/1/049/1/04100%
62Toroid supportIronworker12 hrs9/1/049/1/04100%
62Toroid supportMech. Tech8 hrs9/1/049/1/04100%
63HP102 supportIronworker12 hrs9/2/049/2/04100%
63HP102 supportMech. Tech8 hrs9/2/049/2/04100%
64VP103 supportIronworker12 hrs9/2/049/2/04100%
64VP103 supportMech. Tech8 hrs9/2/049/2/04100%
65HP104 supportIronworker12 hrs9/3/049/3/04100%
65HP104 supportMech. Tech8 hrs9/3/049/3/04100%
66VP105 supportIronworker12 hrs9/3/049/3/04100%
66VP105 supportMech. Tech8 hrs9/3/049/3/04100%
67PM105 supportIronworker12 hrs9/6/049/6/04100%
67PM105 supportMech. Tech8 hrs9/6/049/6/04100%
68 VP106 supportIronworker12 hrs9/6/049/6/04100%
68 VP106 supportMech. Tech8 hrs9/6/049/6/04100%
69HP107 supportIronworker12 hrs9/7/049/7/04100%
69HP107 supportMech. Tech8 hrs9/7/049/7/04100%
70PM107 supportIronworker12 hrs9/7/049/7/04100%
70PM107 supportMech. Tech8 hrs9/7/049/7/04100%
71VP108 supportIronworker12 hrs9/8/049/8/04100%
71VP108 supportMech. Tech8 hrs9/8/049/8/04100%
72PM108 supportIronworker12 hrs9/8/049/8/04100%
72PM108 supportMech. Tech8 hrs9/8/049/8/04100%
73HP109 suupportIronworker12 hrs9/9/049/9/04100%
73HP109 suupportMech. Tech8 hrs9/9/049/9/04100%
74VP110 supportIronworker12 hrs9/9/049/9/04100%
74VP110 supportMech. Tech8 hrs9/9/049/9/04100%
75VP111 supportIronworker12 hrs9/10/049/10/04100%
75VP111 supportMech. Tech8 hrs9/10/049/10/04100%
76HP112 supportIronworker12 hrs9/10/049/10/04100%
76HP112 supportMech. Tech8 hrs9/10/049/10/04100%
77PM112 supportIronworker12 hrs9/13/049/13/04100%
77PM112 supportMech. Tech8 hrs9/13/049/13/04100%
78Swab out magnetsVacuum tech32 hrs8/30/048/31/04100%
79Check magnets for obstructionsEngineer/Physicst32 hrs9/1/049/2/0470%
80Install Instrumentation & vacuum pipe (BPM's, PMs, toroid, RWM)Vacuum tech480 hrs9/3/049/30/04100%
81Install VP101Vacuum tech24 hrs9/3/049/3/04100%
82Install HP101Vacuum tech24 hrs9/6/049/6/04100%
83Install PM101Vacuum tech24 hrs9/7/049/7/04100%
84Install RWMVacuum tech24 hrs9/8/049/8/04100%
85Install ToroidVacuum tech24 hrs9/9/049/9/04100%
86Install HP102Vacuum tech24 hrs9/10/049/10/04100%
87Install VP103Vacuum tech24 hrs9/13/049/13/04100%
88Install HP104Vacuum tech24 hrs9/14/049/14/04100%
89Install VP105Vacuum tech24 hrs9/15/049/15/04100%
90Install PM105Vacuum tech24 hrs9/16/049/16/04100%
91Install VP106Vacuum tech24 hrs9/17/049/17/04100%
92Install HP107Vacuum tech24 hrs9/20/049/20/04100%
93Install PM107Vacuum tech24 hrs9/21/049/21/04100%
94Install VP108Vacuum tech24 hrs9/22/049/22/04100%
95Install PM108Vacuum tech24 hrs9/23/049/23/04100%
96Install HP109Vacuum tech24 hrs9/24/049/24/04100%
97Install VP110Vacuum tech24 hrs9/27/049/27/04100%
98Install VP111Vacuum tech24 hrs9/28/049/28/04100%
99Install HP112Vacuum tech24 hrs9/29/049/29/04100%
100Install PM112Vacuum tech24 hrs9/30/049/30/04100%
101Install loss monitorsInst. Tech160 hrs10/1/0410/14/04100%
102Rough align Instrumentation & vacuum pipeSurveyor168 hrs9/27/0410/5/04100%
103Install vacuum pumps and standsVacuum tech160 hrs10/6/0410/19/04100%
104Terminate and connect Cables (Instrumentation, vacuum, etc.)Inst. Tech408 hrs10/6/0410/28/04100%
105Pump down and Commission Vacuum SystemVacuum tech120 hrs10/20/0410/26/0475%
107Pull Remaining Cables (Instr.,TLM, vacuum, etc.)Electrician880 hrs8/23/049/21/04100%
109Install control in carrier tunnel (upper hobbit)Surveyor24 hrs8/23/048/23/04100%
110Rough align stub magnets (6)Surveyor72 hrs8/24/048/26/04100%
110Rough align stub magnets (6)Mech. Tech24 hrs8/24/048/26/04100%
111Re-reference HV101-1 and HV101-6Surveyor48 hrs8/27/048/30/04100%
112Remove 2 sight riser plugs at MI-60Ironworker24 hrs8/26/048/26/04100%
113Vertical drops @ 4 SR (2 @MI-60 + SR1+SR2)Surveyor96 hrs8/31/049/3/04100%
114Level run between MI-60 to SR2 (Pre-Tgt) aprox 1500 ftSurveyor120 hrs9/6/049/10/04100%
115Tie Stub to Pre-Tgt network (through Carrier Tunnel) areaSurveyor120 hrs9/13/049/17/04100%
116Tie Stub network to MI-60 (ties to SRs)Surveyor72 hrs9/20/049/22/04100%
117Final alignment of magnets MI thru Q104Surveyor216 hrs10/11/0410/21/04100%
118Final alignment of magnets and inst. Q104 thru NuMI stubSurveyor504 hrs10/22/0411/19/0440%
119Final alignment of magnets and inst. ds of hobbit door thru Horn2Surveyor288 hrs11/22/0412/7/040%
120Re-align D614 at Mi-60Surveyor12 hrs11/22/0411/22/040%
122Remove 614-1 MI dipole and store in alcoveMech. Tech12 hrs8/23/048/23/04100%
123Install drip tray over LCW pipeMech. Tech16 hrs8/23/048/23/04100%
124Remove hoses on Q111,Q112LCW Tech2 hrs8/24/048/24/04100%
125Install cooling plates on Q111,Q112Mech. Tech32 hrs8/24/048/26/04100%
126Connect LCW to Q111,Q112 and cooling platesLCW Tech8 hrs8/26/048/27/04100%
127Install additional fansMech. Tech32 hrs8/27/048/31/040%
128Recycler Dept specify final locations of temp probesEngineer/Physicst8 hrs8/31/049/1/040%
129Move temp probes to new locations if necessaryMech. Tech16 hrs9/1/049/2/040%
130Re-insert MI-60 sight riser plugsIronworker24 hrs9/23/049/23/040%
131Reinstall 614-1 at Mi-60Mech. Tech12 hrs11/22/0411/22/040%
133Power supply tests (evenings)EE Tech240 hrs11/1/0411/19/040%
134Subsystem checkoutAll support groups72 hrs10/29/0411/10/041%
196Field direction checks (all magnets) (end of shutdown)Interlock tech8 hrs11/9/0411/9/040%
196Field direction checks (all magnets) (end of shutdown)Engineer/Physicst8 hrs11/9/0411/9/040%
197Beamline Testing (exercise components)Engineer/Physicst280 hrs11/11/0411/19/040%