MI-65 Remaining Tasks





Project Start:
Project Finish:
11/8/04
2/7/05


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
PV-9 Pumps Upgrade
5 days12/11/0412/16/04 75%
2
Repair/Install Pump / Test
5 days12/11/0412/16/04 75%
3
Carrier / PreTarget Final Alignment
11 days12/13/0412/24/04 19%
4
SR2 & SR3
3 days12/13/0412/15/04 70%
5
Analyze Data
5 days12/16/0412/21/04 0%
6
Survey Beam Elements as necessary
3 days12/22/0412/24/04 0%
7
Target Module
34 days12/13/041/24/05 36%
8
Alignment
3 days12/13/0412/15/04 100%
9
Installation Using Cameras
1 day12/16/0412/16/04 100%
10
Test Insert Blue Block Using Cameras
1 day12/17/0412/17/04 0%
11
Test Install L Block Uising Cameras
1 day12/18/0412/18/04 0%
12
Final Survey Insitu
3 days12/20/0412/22/04 0%
13
Target Helium Vacuum System
2 days1/21/051/24/05 0%
14
Horn RAW Skids
6 days12/13/0412/18/04 83%
15
Replace Pump - Horn 2
4 days12/13/0412/16/04 100%
16
Initialize and Balance - Horns 1 & 2
2 days12/17/0412/18/04 50%
17
Miscellaneous Target Hall Tasks
43 days?12/13/042/4/05 30%
18
Move "T" Block Storage
0.5 days12/27/0412/27/04 0%
19
Seal Downstream "R" Blocks Seams
3 days12/27/0412/29/04 0%
20
Install Pre-Target Hatch Blocks
2 days12/13/0412/14/04 100%
21
Fence Stripline
10 days1/21/052/3/05 0%
22
Crane Access Platform
10 days12/13/0412/23/04 80%
23
Seal Penetrations - Fire walls & Doors
2 days1/3/051/4/05 0%
24
Spare Magnet Storage
3 days1/21/051/25/05 0%
25
Remove Crane Controls for Beam Ops
1 day2/4/052/4/05 0%
26
6" Poly Shielding @ Stripline
1 day12/13/0412/13/04 0%
27
Monitoring Holes-Decay Pipe Concrete
2 days12/15/0412/16/04 100%
28
Thermocouples @ Decay Pipe
5 days1/17/051/21/05 0%
29
Electronics Checkout
42 days12/13/042/3/05 30%
30
Wall Scale for Crane Position
1 day?1/3/051/3/05 0%
31
Horn Pulse Tests
1 day12/20/0412/20/04 0%
32
Power Supply Tests
18 days12/18/041/11/05 0%
33
Weekends
18 days12/18/041/11/05 0%
34
Hot Horn Handling
9 days1/3/051/13/05 0%
35
Install Thermocouples @ Horns
2 days1/3/051/4/05 0%
36
Beam Test
2 days1/15/051/16/05 0%
37
Place R Block Cover
4 days1/17/051/20/05 0%
38
Stripline Penetration Seals
3 days1/17/051/19/05 0%
39
Concrete and Seal "R" Block Butress
3 days1/17/051/19/05 0%
40
Search and Secure Fence
4 days1/17/051/20/05 0%
41
Target Chase Air System
42 days12/13/042/3/05 32%
42
Sheet Metal
11 days12/13/0412/24/04 51%
43
Instrumentation
7 days12/13/0412/20/04 90%
44
"R" Block Damper
10 days12/13/0412/23/04 30%
45
Heat Exchanger Dampers & Linkages
5 days12/20/0412/24/04 40%
46
Electrical
26 days12/13/041/14/05 37%
47
Service - VFD (RAW Room) to 100 HP Fan
10 days12/13/0412/23/04 70%
48
Service to Supply Duct Reheat Coils
4 days12/16/0412/20/04 100%
49
Service to chiller
5 days1/3/051/7/05 0%
50
Chiller Controls
5 days1/10/051/14/05 0%
51
Instrument cable pulls and terminaitons
6 days1/3/051/10/05 0%
52
Mechanical Piping & Pnuematic Controls
21 days12/13/041/7/05 24%
53
Compressed Air Line & Slave Tank
7 days12/13/0412/20/04 70%
54
Compressed Air Distribution
5 days1/3/051/7/05 0%
55
Heat Exchanger Supply & Return Lines
12 days12/17/0412/31/04 17%
56
Chiller Unit
5 days1/3/051/7/05 0%
57
Commissioning Air System
10 days1/21/052/3/05 0%
58
Target Shield Door Installation
27 days12/15/041/17/05 30%
59
Place Moveble Base on Mezz
2 days12/15/0412/16/04 100%
60
Fixed Side
10 days12/17/0412/29/04 60%
61
Moveable Side of Shield Door
12 days12/30/041/14/05 0%
62
Hydraulics
3 days1/15/051/17/05 0%
63
Above Gound Tasks
23 days12/13/041/11/05 50%
64
Drain Holes - EAV 1,2,3,&4
3 days12/13/0412/15/04 100%
65
Repair Manhole
1 day1/10/051/10/05 0%
66
EAV-3 VFD
2 days1/10/051/11/05 0%
67
Instrument Piping - RAW Penetration
4 days12/13/0412/16/04 100%
68
Fire Door Lights
5 days1/10/051/14/05 0%
69
Ready For Beam
1 day2/7/052/7/05 0%

Resources


IDNameGroupMax UnitsPeak Units

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete