October 2004

Sunday Monday Tuesday Wednesday Thursday Friday Saturday
 
 
 
 
 
 
1
Coil water connection work is complete, aside from final connection to the water skids. The Booster skid is being  moved to allow more room for the PS.

Coil PS bus installation begins.

Muon Alcoves - 2 Minos people from U Wisconsin working.

Absorber - parts arrived. One manifold is installed, 2nd (of two) is in progress.

Sump control panel repairs in progress - Sump #4 running with pressure readback.
2

 
 
 
 
3
Projected Work:
• Continue Coil PS & Water System Inst
• Continue Detector Commissioning.


4

 
 
 
 
5

 
 
 
 
6

 
 
 
 
7

 
 
 
 
8

 
 
 
 
9

 
 
 
 
10
Projected Work:
• Continue Coil PS & Water System Inst
• Continue Detector Commissioning.
11

 
 
 
 
12

 
 
 
 
13

 
 
 
 
14

 
 
 
 
15

 
 
 
 
16

 
 
 
 
17
Projected Work:
• Continue Detector Commissioning.
18

 
 
 
 
19

 
 
 
 
20

 
 
 
 
21

 
 
 
 
22

 
 
 
 
23

 
 
 
 
24
Projected Work:
• Continue Detector Commissioning.
25

 
 
 
 
26

 
 
 
 
27

 
 
 
 
28

 
 
 
 
29

 
 
 
 
30

 
 
 
 
31